How can you generate different scheduling solutions?

The application only generates one scheduling solution. However the application can also provide other solutions.

In the “Scheduling” tab you can use the “Multi solutions” process in order to generate different scheduling solutions.

It can be done in two different ways:

  • Chosen solutions: the application will generate six classical solutions.

1. Click on “Multi solutions” and by default, this option is selected.

2. Select the indicators you want to use for the comparison (by default, all of them are ticked).

3. Click on “OK” and  the comparison process will start.

4. Observe the results in a graphical view (selected by default) or in a numerical view.

The most the ball is filled the most the solution meets the criterion.

5. Double click on the solution you choose and this solution will be displayed by the application.

  • Solution finder: the application will compare all the possible solutions.

1. Click on “Multi solutions” and select this option.

2. Select the indicators you want to use for the comparison (by default, all of them are ticked).

3. Click on “OK” and  the comparison process will start.

 